Prudence Road at Pruden Center Entrance

Update: February, 15, 2024 

The inside lanes in both directions will be closed, directing traffic to the single outside East and Westbound lanes. This adjustment is to allow for the construction of a raised median. The anticipated date for the traffic shift is as early as February 26, 2024, subject to weather conditions. 

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7

The project consists of intersection improvements at Pruden Boulevard (US 460) and Prudence Road to allow for left turn movements both north and south of Pruden Boulevard. The existing typical section which consists of an undivided four lane roadway with minimal shoulders and ditches will be replaced with a raised median separating two-way traffic and protecting left turn movements and curb and gutter along the south side of the roadway.


Contact

Luke Drylie, Project Manager

ldrylie@suffolkva.us

Phone:  514-7708

Plans

Capture

BUDGET

The budget for this project $5,532,455 using a combination of state and local funds.

Preliminary Engineering:  $300,500
Right of Way Acquisition: $851,065
Construction:                    $4,380,890

TIMELINE

Preliminary Engineering: Jan 2018 – Feb 2020
Right of Way Acquisition: Feb 2020 – Sep 2022
Construction:                    April 2023 – June 2024