Nansemond Parkway / Wilroy Road Overpass

WATCH THE PROJECT AS IT HAPPENS

IMAGES UPDATED EVERY TEN MINUTES.

Nansemond Wilroy Overpass Project - View 1 (Suffolk, VA)

OxBlue Construction Cameras

Nansemond Wilroy Overpass Project - View 2 (Suffolk, VA)

OxBlue Construction Cameras

The project proposes to eliminate the existing at-grade crossing by realigning the intersection of Nansemond Parkway and Wilroy Road in order to provide a grade separated overpass for Nansemond Parkway over the Commonwealth Railway tracks. Projected construction 2023.

Project Manager: Courtney Barrett

cbarrett@suffolkva.us

Phone: 514-7687

Public Hearing Submittal

Public Hearing Submittal

Brochure

brochure nw

Nansemond Pkwy Wilroy Rd Overpass Response Letter

IMG_4969

100% Plan Set

100% Plans

Overpass Improvements Base Layout

Overpass Improvements Base Layout

Bridlewood Figure

Bridlewood Figure

Project Alignment relationship to Environmental and Historic Resources

historic  environmental

Rail Crossing Safety Study

Nansemond Parkway and Wilroy Road Rail Safety Study

Traffic Study - Final Version

Nansemond Parkway and Wilroy Traffic Study

BUDGET

Preliminary Engineering:  $1,301,450    
Right of Way Acquisition: $3,700,683
Construction:                    $22,476,608
Total Budget:                  $27,478,741 

TIMELINE

Preliminary Engineering:  August 2017 – April 2021
Right of Way Acquisition: April 2021 – January 2023
Construction:                    May 2023 – July 2025