Nansemond Parkway/Wilroy Rd Overpass

The project proposes to eliminate the existing at-grade crossing by realigning the intersection of Nansemond Parkway and Wilroy Road in order to provide a grade separated overpass for Nansemond Parkway over the Commonwealth Railway tracks. Projected construction 2021.

Project Manager: Mitch Conner

mdconner@suffolkva.us

Phone: 514-7626

Brochure

brochure nw

Nansemond Pkwy Wilroy Rd Overpass Response Letter

IMG_4969

Plans

Plan Set

Overpass Improvements Base Layout

Overpass Improvements Base Layout

Bridlewood Figure

Bridlewood Figure

Project Alignment relationship to Environmental and Historic Resources

historic  environmental

Rail Crossing Safety Study

Nansemond Parkway and Wilroy Road Rail Safety Study

Traffic Study - Final Version

Nansemond Parkway and Wilroy Traffic Study

BUDGET

Preliminary Engineering:  $1,301,450    
Right of Way Acquisition: $3,700,683
Construction:                    $22,476,608
Total Budget:                  $27,478,741 

TIMELINE

Preliminary Engineering:  August 2017 – January 2021
Right of Way Acquisition: February 2021 – October 2022
Construction:                    October 2022 – October 2024