Diverging Diamond Interchange

Convert the Godwin Blvd (SR 10/32) interchange with the Suffolk Bypass (US 460/58/13) from a partial cloverleaf design to a diverging diamond interchange (DDI). The on-ramps in the NW & SE quadrants will be widened. The eastbound Suffolk Bypass off-ramp to Godwin Boulevard will be on new alignment.

Diverging Diamond
Project Location

Project Manager

G. Allan Mushett PE, PMP CIP Engineering Manager

757 514-7681


BUDGET

Preliminary Engineering: $1,698,000
Right of Way Acquisition:$541,000
Construction:                   $14,401,000
Total Budget:                 $16,401,000

TIMELINE

Preliminary Engineering: October 2022 - March 2024
Right of Way Acquisition: March 2024 - August 2025
Construction:                   August 2025 - October 2027