AAA Rated Standard & Poors July 2014

Road Closures & Possible Traffic Delays

July 2, 2015

Road Closures and Possible Traffic Delays

SUFFOLK, VA (July 2, 2015) The following roads in the City of Suffolk will have closures that could cause delays, Thursday, July 2, 2015 due to construction and maintenance projects.

 New Projects:

 (Ruritan Boulevard) – Suffolk Department of Public Works will have a right lane closure in the 6700 block on the east side of Ruritan Boulevard for a sidewalk installation from 9 a.m. to 2:30 p.m.

 (Route 58) – Suffolk Department of Public Works will have a mobile operation on westbound Route 58 between Brentwood Road and the Southampton line for asphalt repair from 9 a.m. to 3 p.m.

 (Route 58) – Suffolk Department of Public Works will have a mobile operation on westbound Route 58 from the Chesapeake City Line to Holland Road for drainage maintenance from 9 a.m. to 3 p.m.

(Babbtown Road) – Suffolk Department of Public Works will have a flagging operation on Babbtown Road between Whaleyville Boulevard and Carolina Road for drainage maintenance from 10 a.m. to 3 p.m.

 (Saratoga Street) – A contractor will have a flagging operation on Saratoga Street between West Washington Street and Jackson Street from 10 a.m. to 3 p.m.

 (South Quay Road) – A contractor will have a mobile operation on South Quay Road for vegetation maintenance from 9 a.m. to 11 a.m.

(Manning Bridge Road) – Suffolk Department of Public Works Traffic Engineering Paint Crew will have a work zone on Manning Bridge Road between Manning Road and Route 58 from 8:30 a.m. to 1 p.m.

 Ongoing Projects:

 (Godwin Boulevard) – A contractor is working in the right-of-way along the east side of Godwin Boulevard between Harrell Drive and the Virginia Dominion Power facility right-of-way along Pembroke Lane and at Kings Highway in the vicinity of the Chuckatuck Fire Department. Flagging operations may be required. This work is scheduled to be completed by September 1, 2015.

 (Route 58/Portsmouth Boulevard) – A contractor working at the Park and Ride will have the westbound right shoulder on Route 58/Portsmouth Boulevard, between C Street and Nansemond Parkway, closed June 10 thru July 14 to facilitate installation of a turn lane for the parking lot.

 (Shoulders Hill Road) - A contractor will be constructing a new water transmission main along the Shoulders Hill Road Project. The project is scheduled to begin in early April and be completed by August 15, 2015. From June 15, 2015 to August 15, 2015, the northbound lane will be closed and detours will be in place. For more information and updates please visit: http://www.shouldershillwatermain.com.

 (Various locations) – A contractor will be working on the installation of water and sewer mains for the Crittenden/Eclipse water and sewer extension project. The work hours will be from 7 a.m. to 4 p.m., Monday thru Friday. The project will be ongoing until Summer 2015. Flagging operations will be necessary on the following streets: Wigneil Street, Vine Street, Pike Street during the period of construction.

 (Bennetts Pasture Road and Route 17/Bridge Road) – A contractor will be working at the intersection of Bennetts Pasture Road & Route 17/Bridge Road for the installation of turn lanes. Ongoing work will continue for several months with flagging operations from 9 a.m. to 3 p.m. Moderate to heavy traffic patterns should be anticipated.

 (Turlington Park Neighborhood) – A contractor will be working on the installation of the sewer mains for the Turlington Park Neighborhood. The work hours will be 7 a.m. to 4 p.m., Monday thru Friday. Anticipate detoured traffic in the neighborhood as the sewer mains are being constructed. The project scheduled completion date is October 4, 2015.

 (Portsmouth Boulevard and Nansemond Parkway) - A contractor will be reconstructing the commuter parking lot at the old VDOT weigh scales near the intersection of Portsmouth Boulevard and Nansemond Parkway. The hours of operation are from 7:30 a.m. to 5 p.m., Monday thru Friday. All commuters who use this lot are directed to use the designated parking area in the Food Lion parking lot at the intersection of Portsmouth Boulevard and Suburban Drive. Anticipate limited short term lane closures.

(Shoulders Hill Road) - A Suffolk Department of Public Utilities contractor will begin constructing a new water transmission main along Shoulders Hill Road Project to enhance fire flows within the area. The project is scheduled to begin in early April and be completed by August 15, 2015. From early April through June 12, 2015, construction will be limited from 9 a.m. to 3 p.m., Monday through Friday. From June 13, 2015 to August 15, 2015, the northbound lane will be closed and the detours will be in place. Click here for more information.

Suffolk Seal
Copyright © 2015 City of Suffolk, Virginia
All rights reserved.

Sign up for our newsletter!
Email:


Web site problems, comments and/or suggestions? Contact Us