BUDGET
Preliminary Engineering: $2,121,900
Right of Way Acquisition:$1,892,914
Construction: $7,060,186
Total Budget: $11,075,000
TIMELINE
Preliminary Engineering: August 2015 – February 2022
Right of Way Acquisition: February 2022 – June 2023
Construction: June 2023 – October 2024