Longstreet Lane Bridge Replacement

Existing bridge and adjacent roadway approach will be dismantled and removed for the construction of the new bridge and roadway approach.

The new bridge will be elevated approximately 1.5 ft. higher than the existing conditions. The length of the new bridge will be about 183 ft. and 23’- 4” wide.  


Contact

Project Engineer:

Ali Huazy  

Phone:  514-7712

long
  1. 1
  2. 2

Budget

Preliminary Engineering:         $333,000

Right of Way Acquisition:        $2,500

Construction:         $2,253,852

Total:         $2,589,652


Timeline

July 2019 – Began Design

January 2022 – Right of Way Acquisition to begin

May 2022 – Project Advertisement

August 2022 – Award Contract 

December 2023 – Planned Finish Date