Elwood Rd Bridge Replacement

The contractor started work on June 24th, 2022 replacing the Elwood Road Bridge (Rte. 613) over Kingsale Swamp. 

The old bridge was a single span steel girder superstructure with timber deck supported on timber substructure spanning approximately 31 ft. which made it structurally and geometrically deficient. It restricted the passage of emergency vehicles and farm equipment.

The new structure will be constructed from prestressed concrete piles and a voided slab span; the anticipated life cycle of the new bridge will be 75 years.  Expected to open in Spring 2023.

Project Engineer:

Ali Huazy

ahuazy@suffolkva.us

Phone: 514-7712

Traffic Detour

Detour - Elwood Rd BRDG Replacement
Elwood Bridge
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5

TIMELINE

Construction -  April 25, 2022 - Spring 2023

Map