Shoulders Hill Road Multi-use Path

This project provides a safer way for pedestrians and cyclist to access amenities in the area.  

The multi-use path is 10 foot wide by 1,100 linear feet along the east side of Shoulders Hill Road from Weatherby Way / Belmont Boulevard to Bennett's Creek Park Road.  It is also ADA compliant. 

Other improvements included pedestrian crossings, drainage and new curb and gutter.   

The project was completed in October 2023.

Project Location Map

100% Plan Set

Plan Set

Budget

Preliminary Engineering:     $125,000       

Right of Way/Acquisition:  $25,000        

Construction:                     $630,000      

Total Budget               $780,000    


Timeline        

Preliminary Engineering: September 2020 – February 2022

Right of Way/Acquisition: February 2022 – August 2022

Construction: June 2023 – Fall 2023